CONSTRUCTION OF NEW 110/35/6 KV “BINAGADI” SUBSTATION

Since it was built 70 years ago, the 110/35/6 kV substation “Binagadi” has been reconstructed. All equipment of the 110/35/6 kV substation has been updated to prevent accidents and ensure a reliable and sustainable power supply to the fast-growing industrial and social facilities in the Binagadi, Narimanov and Nasimi districts of Baku.

Construction of a new 110 kV AIS
Installation of 4 power transformers 63 MVA 110/35/6 kV
Construction of an administrative building
Installation of 35 and 6 kV panels
Installation of a modern relay protection and automation system and the creation of a control centre for dispatcher
Construction of an administration building for the regional power network
Construction of a special-purpose vehicle transport zone
Installation of asphalt on area
Installing of water, sewers and other underground communication lines