REBUILDING OF THE LARGEST SUBSTATION “ABSHERON” 500/330/220/10 KV OF STRATEGIC IMPORTANCE IN AZERBAIJAN

The country’s largest substation, 500/330/220/10 kV, the strategically important “Absheron” substation was completely rebuilt. As a result, it was possible to increase the load-bearing capacity of the substation, increase the reliability and stability of the electricity supply, reduce losses and implement innovative solutions that meet modern standards. The installation of modern controls, protective relays and automatic circuits, the prevention of equipment failures and damage, the rapid, selective and reliable operation of guards and the flexibility of operational operations are ensured. Substation management was fully digitized. At the same time, the central SCADA system of the “Azerenerji” OJSC was installed in the dispatcher control room in a fully redundant version.

Construction of 500, 330 and 220 kV AIS
Construction of a control centre building
Construction of an engineer dormitory building
Construction of a modern digital type relay protection and automation system, SCADA system and creation of a dispatcher control center
Installation of asphalt on area
Installing of water, sewers and other underground communication lines
Landscaping works